Information and data of programs, tasks, public investment projects on the National Information System and Database of Vietnam

Information and data of programs, tasks, public investment projects on the National Information System and Database of Vietnam
Quoc Tuan

On October 16, 2024, the Minister of Planning and Investment of Vietnam issued Circular 19/2024/TT-BKHDT regulating the formulation, appraisal, assignment, adjustment, monitoring, and evaluation of plans, programs, tasks, and public investment projects on the National Information and Database System on Public Investment in Vietnam.

Information and data of programs, tasks, public investment projects on the National Information System and Database of Vietnam

- Information and data of programs, tasks, projects, and other public investment objects on the System: Program codes, task codes, project codes, and other public investment codes provided by the System; The agency code associated with the budget for programs, tasks, projects, and other public investment objects provided by the System of the Ministry of Finance; information on the approval of investment policy for programs, projects, information on the Decision approving the cost estimates for project preparation tasks, planning tasks, information on the Investment Decision, and adjustment decisions (if any); the status of the project as required by the System.

- Information and data on the public investment plan, project implementation status, and disbursement: The information and data stipulated in this section will be aggregated by the System from the content of the implementation status report stipulated in Article 13 of Circular 19/2024/TT-BKHDT.

- Documents and materials of the program, task project must be uploaded to the System:

+ The investor or project component manager shall upload the following documents to the System within 07 working days from the date of issuance, including:

++ Decision  approving  the  task,  cost  estimates  for  investment  preparation;

++ Resolution,  Decision  approving  or  adjusting  the  investment  policy  (if  any);

++ Investment  Decision,  Adjustment  Investment  Decision  (if  any);

++ Resolution,  Decision  on  allocating  or  adjusting  medium-  and  annual-term  public  investment  plans  by  competent  authorities;

++ Decision  approving  the  final  settlement  of  investment  capital  for  project  completion;

+ The Program Manager shall upload to the System within 07 working days from the date of issuance, including:

++ Resolution  by  competent  authorities  approving  the  investment  policy  of  the  public  investment  program;

++ Decision  by  the  Prime  Minister  of  Vietnam  approving  the  public  investment  program;

+ Documents uploaded on the System must be scanned from the original document in color or electronic documents with digital signatures;

+ Besides the above-mentioned information and documents, investors, component project managers, and program managers are encouraged to fully update documents according to the System's functionalities.

View detailed content at Circular 19/2024/TT-BKHDT dated October 16, 2024.

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;