Contents of the estimated norms for digging and clearing landslides in overcoming natural disaster consequences and ensuring traffic in Vietnam

Contents of the estimated norms for digging and clearing landslides in overcoming natural disaster consequences and ensuring traffic in Vietnam
Que Anh

On December 31, 2024, the Minister of Transport of Vietnam issued Circular 67/2024/TT-BGTVT promulgating the norms for estimating excavation and removal of landslide soil and rock in efforts to remedy natural disaster consequences and ensure transportation on roadways.

Contents of the estimated norms for digging and clearing landslides in overcoming natural disaster consequences and ensuring traffic in Vietnam

Excavation and clearing of landslides in the context of disaster recovery, ensuring traffic safety on roads (hereinafter referred to as landslide excavation and clearing activities) is an operation carried out immediately when the disaster subsides or immediately after the weather returns to normal, aiming to restore traffic operations as quickly as possible, ensuring safe and uninterrupted traffic.

The content of cost estimate norms for excavation and clearing of landslides in disaster recovery, ensuring traffic safety on roads is as follows:

The cost estimate norms for landslide excavation and clearing work include: code, work name, unit of measure, work component, and a table of cost norms, in which:

- The work component specifies the content of the steps from preparation to completion of landslide excavation and clearing work according to the specific technical conditions and construction methods.

- The table of cost norms includes:

+ Labor cost norms: the number of labor days of direct workers and support workers needed to complete one unit of landslide excavation and clearing work from preparation to completion. The labor cost is calculated in labor days according to worker grade; the worker grade is the average grade of direct workers and support workers participating in executing one unit of landslide excavation and clearing work.

+ Construction machinery cost norms: the number of operating shifts of construction machinery to complete one unit of landslide excavation and clearing work.

Refer to more details in the Circular 67/2024/TT-BGTVT effective from February 15, 2025.

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;