What are the responsibilities of investors of electricity projects in implementation of plans on electricity development in Vietnam?

Recently, the Government of Vietnam issued Decree 137/2013/ND-CP detailing implementation of the Electricity Law and the Law on amending the Electricity Law

What are the responsibilities of investors of electricity projects in implementation of plans on electricity development in Vietnam?

What are the responsibilities of investors of electricity projects in implementation of plans on electricity development in Vietnam? (Internet image)

Decree 137/2013/ND-CP stipulates the responsibilities of investors of electricity projects in management and implementation of plans on electricity development in Vietnam as follows:

  •  Allocate fully and timely funding for units implementing compensation, residential removal, resettlement of electricity projects;
  • Submit dossiers related to the land grant for premises, safe corridors, workers’ housing areas, resettlement areas of electricity projects to People’s Committees of provinces and central-affiliated cities;
  • To coordinate with units according to decisions of competent state agencies in performing the work of compensation, removal, resettlement for carrying compensation, support for removal, resettlement and ground clearance;
  • Annually report to state agencies competent to management on implementation of plans on electricity development about situation of plan implementation.

At the same time, organizations and individuals possessing houses and property attached to land area in scope of premises, safe corridors of electricity projects shall:

- Implement properly with deadlines of handing over premises in decisions of People’s Committees at all levels for land area used for electricity projects as prescribed by law on land;

- To coordinate with units implementing the work of compensation, removal, resettlement, in clearance of premises and safe corridors for projects on electric sources, power grid already been decided for investment by competent state agencies.

More details can be found in Decree 137/2013/ND-CP, which comes into force from December 10, 2013.

Ty Na

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

5 lượt xem



Related Document
  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;