The Ministry of Planning and Investment of Vietnam issued the Circular No. 09/2018/TT-BKHĐT providing guidance on the implementation of the Government’s Decree No. 63/2018/ND-CP on investment in a public-private partnership form.
According to the Circular No. 09/2018/TT-BKHĐT of the Ministry of Planning and Investment of Vietnam, feasibility study report refers to a document describing subject matters of the study relating to the necessity, feasibility and efficiency of a PPP project. Documentation included in the application package for evaluation of FSR shall comprise:
- Application document for approval of the feasibility study report;
- Full texts of the feasibility study report;
- Full texts of the written agreements between Ministries, sectoral administrations or provincial-level People’s Committees and investors to authorize investors to prepare feasibility study reports (with respect to projects proposed by investors);
- Decision on approval of the policy on investment in a project (except group-C projects);
- Other relevant legislative materials and documents.
Also according to the Circular No. 09/2018/TT-BKHĐT, a feasibility study report includes:
- Necessity of an investment project;
- Technical Interpretation of a project;
- Impacts on environment, society, national defence and security;
- Demand forecasting;
- Analysis of socio-economic effectiveness;
- Financial analysis;
- Project contract type;
- Analysis of risks arising during the project implementation period;
- State support measures;
- Project implementation plan;
- Management of project implementation.
View more details at the Circular No. 09/2018/TT-BKHĐT of the Ministry of Planning and Investment of Vietnam, effective from February 15, 2019.
- Thanh Lam -
Address: | 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City |
Phone: | (028) 7302 2286 |
E-mail: | info@lawnet.vn |