Vietnam: Fees for assessment of construction cost estimate according to Circular 210

This content is specified in Circular No. 210/2016/TT-BTC of the Ministry of Finance of Vietnam providing for fees for assessment of technical designs and construction cost estimate collection, transfer, management and use thereof.

Specifically, fees for assessment of construction cost estimate in case of three-stage design; assessment of construction drawing designs and construction cost estimate in case of two-stage design specified in Circular No. 210/2016/TT-BTC of the Ministry of Finance of Vietnam are as follows:

Unit: %

No.

Type of work

VAT-exclusive construction cost specified in approved construction cost estimate or construction contract cost estimate (billion VND)

≤15

50

100

200

500

1.000

2.000

5.000

8.000

1

Civil work

0,160

0,106

0,083

0,062

0,046

0,038

0,028

0,021

0,018

2

Industrial work

0,185

0,121

0,094

0,072

0,055

0,041

0,033

0,023

0,020

3

Traffic work

0,106

0,068

0,054

0,041

0,031

0,024

0,020

0,014

0,012

4

Work for agricultural and rural development

0,117

0,076

0,060

0,046

0,035

0,026

0,022

0,016

0,014

5

Infrastructure work

0,122

0,082

0,062

0,047

0,037

0,029

0,024

0,017

0,014

 

View full text at Circular No. 210/2016/TT-BTC of the Ministry of Finance of Vietnam, effective from January 01, 2017.

- Thanh Lam -

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

34 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;