On April 29, 2014, the Ministry of Transport of Vietnam issued Circular 11/2014/TT-BGTVT guiding the design, construction, and acceptance of pedestrian suspension bridges.

13  Requirements  for  Occupational  Safety  when  Constructing  Bridge  Components  and  Other  Structures,  Circular  11/2014/TT-BGTVT

Vietnam: 13 requirements regarding occupational safety during the construction of components and other structures of suspension bridges (Illustrative photo)

Circular 11/2014/TT-BGTVT provides general guidelines on requirements regarding occupational safety during the construction of components and other structures of pedestrian suspension bridges in Vietnam as follows:

- Units carrying out the fabrication and erection of components must fully comply with technical requirements regarding occupational safety as prescribed by TCVN Standard 8747:2012 and other relevant legal provisions.

- Each production area and workplace must have safety rule boards that everyone must adhere to.

- The production workshop must be equipped with adequate lighting and ventilation to ensure industrial hygiene.

- Cutting, welding, and painting work must not be conducted in the same workshop or adjacent areas to prevent fire and explosion. Fire and explosion safety must be implemented according to TCVN 3254-86 and 3255-86.

- All workers must be fully equipped with personal protective equipment when working.

- Workers must wear life jackets when working on the river.- Heavy load installation of the bridge must have a signaler coordinating smoothly.

- There must be a specialized safety inspection department.

- Each construction team must have safety officers wearing red armbands during work shifts to remind everyone in case potentially unsafe situations arise.

- Safety measures must be taken when working at heights to prevent falls.

- Safety measures must be in place when arranging the construction electrical network.

- Rescue equipment must be available when working on river sections.

- Construction and erection must not be carried out during storm seasons. Stability measures must be increased in case of wind level 5 or higher.

Details may be found in Circular 11/2014/TT-BGTVT effective from June 15, 2014.

Ty Na

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;