The Ministry of Finance of Vietnam issued Circular 09/2016/TT-BTC regulating the final settlement of projects completed under the state capital.
The settlement deadline is guided in Article 22 of Circular 09/2016 as follows:
Project | National level | Group A | Group B | Group C |
- Deadline for submitting settlement documents for approval | 09 months | 09 months | 06 months | 03 months |
- Time for verification and approval of settlement | 07 months | 04 months | 02 months | 01 month |
Note:
- The deadline for submitting project completion settlement documents for approval by the competent authority in Vietnam is calculated from the date of signing the handover minutes putting the project's works into use;
- The time for verification and approval of settlement in Vietnam is counted from the date of receipt of all settlement documents as prescribed in Article 8 of Circular 09.
Circular 09/2016/TT-BTC officially takes effect from March 5, 2016.