Circular 119/2016/TT-BQP was issued by the Ministry of National Defense on August 30, 2016, detailing specific steps for the inspection of NitroGlyxerin generating equipment.
Circular 119 stipulates that safety technical inspection must be conducted according to the following steps:
- Step 1. Prepare for inspection;- Step 2. Check technical documents;- Step 3. External and internal inspection;- Step 4. Technical testing inspection;- Step 5. Operational inspection;- Step 6. Process inspection results.
Note:
- The subsequent steps can only be carried out if the results of the preceding step meet the requirements.- All inspection results of each step must be fully recorded in the field log and kept entirely at the inspection organization.
See details Circular 119/2016/TT-BQP effective from October 15, 2016.
-Thao Uyen-