Circular 123/2016/TT-BQP was issued by the Ministry of National Defense on August 30, 2016, specifying the steps for safety inspection of Nitrogen stations.
Circular 123 stipulates that during the technical safety inspection of a nitrogen station, the organization conducting the inspection must perform the following steps sequentially:
- Step 1. Inspection preparation;- Step 2. Review of technical documentation;- Step 3. External and internal inspection;- Step 4. Technical testing;- Step 5. Operational testing;- Step 6. Processing of inspection results.
Note:
- Subsequent inspection steps can only be conducted if the results of the preceding step meet the requirements.- All inspection results of each step must be fully recorded in the field notes and retained at the inspection organization.
See details in Circular 123/2016/TT-BQP, effective from October 15, 2016.