In 2016, the Ministry of Transport issued Circular 17/2016/TT-BGTVT detailing the management and operation of airports.
According to the provisions of Circular 17/2016/TT-BGTVT, the public announcement of airport planning is carried out as follows:
- Within 30 days from the date of approval, the airport planning must be publicly announced.- The Ministry of Transport organizes the announcement of the overall master plan for the development of the national airport system; presides and collaborates with the relevant provincial People’s Committee to organize the announcement of detailed airport plans.- The Civil Aviation Authority of Vietnam organizes the announcement of the detailed construction plan for functional zones within the airports.
Also according to Circular 17/2016/TT-BGTVT, the dossier for approving the detailed construction plan for functional zones within airports includes:
- A proposal for planning approval;- Planning documents, including planning explanations and related drawings;- Feedback documents from relevant agencies and units;- Explanatory documents for the feedback from relevant agencies and units.
Refer to the land boundary determination at Circular 17/2016/TT-BGTVT effective from December 15, 2016.