Recently, the Government of Vietnam has issued Decree No. 113/2013/NĐ-CP on fine art activities.
According to Decree No. 113/2013/NĐ-CP of Vietnam’s Government, procedures for investment preparation for construction project of monuments and mural paintings are prescribed as follows:
1. Draw up draft for construction project of monuments and mural paintings
- A draft of investment project for construction project of monuments and mural paintings shall be drawn up and sent to a competent agency;
- The draft of the investment project for the construction of monuments or mural paintings shall include: the topic, types of arts, scale, the items, materials and location of the construction; form of investment, expected investment level, capital and duration of the project.
2. Create and select model statue:
- Based on the draft of the project prescribed in Clause 1 of this Article, the investor shall build up regulations and requirements for the creation of model statues. The execution of a model statue is carried out in 2 rounds:
+ Round 1: Model statue of a monument is 70 cm or higher in height; the size of the model statue of a relief or a mural painting shall be in proportion to the monument; with regard to mural paintings or relieves not associated with the monument (independent), a model statue with an area of 80 cm2 may be done with the material to be built; accompanying the description of the artistic idea and fundamental design of the general planning.
+ Round 2: The model statue of monument is developed to 130 cm in height; the size of the model statue of reliefs, mural paintings shall be in proportion to the monument; with regard to mural paintings or reliefs not associated with the monument (independent), a model statue with an area of 120 cm2 may be done with the material to be built; accompanying the description of the artistic idea and fundamental design of the general planning.
- The model statues in rounds 1 and 2 shall be selected by the Art council;
- The investor shall request the agencies competent to decide the investment to approve the model statue selected by the Art council in round 2 as the basis for the establishment of the project, the estimate and the construction design of the work;
- 02 applications for approval of the model statue selected in round 2 shall be sent to a competent authority, each of them shall include:
+ A statement paper;
+ A four-dimensional photo of the model statue selected in round 2 in the size of 18 x 24 cm;
+ The operation record of the Art council.
- The authority entitled to decide the investment shall grant the approval for the model statue within 15 days from the day on which the satisfactory application is received.
View details at Decree No. 113/2013/NĐ-CP of Vietnam’s Government, effective from December 01, 2013.