Decree 70/2010/ND-CP guiding The Law on Atomic Energy regarding nuclear power plants, recently issued by the Government, has specified the procedures for granting construction licenses for nuclear power plants in Vietnam. To be specific:
Procedures for granting construction licenses for nuclear power plants in Vietnam (Internet image)
According to Article 25 of Decree 70/2010/ND-CP, investors of nuclear power plants shall make dossiers of application for construction licenses and submit them to the Ministry of Science and Technology of Vietnam. Such a dossier comprises:
- Regarding validity check period:
Within 15 days after receiving a dossier of an investor, responsible ministries shall check the validity and completeness of the dossier and may request addition of information and documents as prescribed and completion of the dossier within the following time limit:
The Ministry of Science and Technology of Vietnam shall consider and grant a construction license for a nuclear power plant after consulting the National Council for Nuclear Safety.
- Regarding adjustment of construction licenses
When wishing to adjust work designs to be different from their construction licenses, investors shall apply for permission for adjustment of their construction licenses before commencing construction according to adjusted contents.
More details can be found in Decree 70/2010/ND-CP, which comes into force from August 10, 2010.