Planning for the Deployment of the BOT Thermal Power Plant Project

The planning for the implementation of the BOT thermal power plant project is detailed in Circular 23/2015/TT-BCT which stipulates the sequence and procedures for investment in thermal power plant projects in the form of Build-Operate-Transfer contracts, issued on July 13, 2015.

Plan for implementing the BOT thermal power plant project, Circular 23/2015/TT-BTC

Plan for implementing the BOT thermal power plant project (Illustrative image)

To be specific: according to the provisions of Article 6 of Circular 23/2015/TT-BTC, the preparation of the BOT project plan is carried out as follows:

  1. Within 30 days from the date of signing the MOU, the BOT investor must prepare a detailed project implementation plan to be submitted to the General Department of Energy for review and agreement. The contents of the detailed project implementation plan include:

- Preparation and approval of the Construction Site Master Plan for the Power Center (if any): Date of submission of the Master Plan; date of approval of the Master Plan;- Preparation and approval of FS, including: Date of submission of FS; date of approval of FS;- Plan for negotiating the BOT Contract and related documents, including: date of PA negotiation; date of PA signing; expected start date of round 1 negotiation; expected end date of round 1 negotiation; expected start date of round 2 negotiation; expected end date of round 2 negotiation; schedule for negotiating related documents: PPA, LLA, design package contract, equipment, materials and construction supply contracts, and fuel supply contracts; date of signing the investment agreement; date of submitting the application for Investment Registration Certificate; date of official signing of the BOT Contract documents;- Financial closing date;- Commencing and construction, including: official project commencement date; commercial operation date of each unit; commercial operation date of the entire plant.

  1. Within 15 working days from the date of receiving the detailed plan, the General Department of Energy shall respond in writing.

More details can be found in Circular 23/2015/TT-BCT, effective from July 13, 2015.

Thuy Tram

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;