New guidance: Measurement and takeoff of quantities in proportion to the designed size of construction works in Vietnam

Recently, the Minister of Construction of Vietnam has issued Circular No. 17/2019/TT-BXD as a manual for quantity takeoff for construction works.

do boc khoi luong theo dien tich cong trinh xay dung, Thong tu 17/2019/TT-BXD

According to Circular No. 17/2019/TT-BXD of the Ministry of Construction of Vietnam, taking off the quantity in ratio to the size, output or service capacity of a construction work shall serve the purpose of making the preliminary calculation or estimate of total investment or total construction investment according to the construction investment rate-based calculation method.

Specifically, taking off quantities in proportion to the building floor area of a civil or industrial construction work shall be conducted as follows:

- The quantity in ratio to the floor area is the total building area of ​​all floors of a construction work, including basement, semi-basement, technical floor, attic and garrett (if any). The building area of​​a floor includes the surrounding walls (or the internal portions of shared walls) and the ground area of ​​loggias, balconies, stairs, lift wells, technical utility boxes, chimneys.

- Descriptive information, including the height of the building (height of each floor or height of the whole building), the number of floors (including superficial floors and basements), structural properties, main materials used, special foundation reinforcement and other information related to costing activities (if any), should be recorded in the detailed or breakdown bill of quantities.

Quantity takeoff in ratio to the area of traffic bridges is guided as follows:

- Quantity in ratio to the area of a road bridge shall be taken off in proportion to the width of the bridge between the outermost of handrails and the length of the bridge stretching to the abutment end dam.

- Descriptive information, including type of bridge, type of bridge girder, bridge width, span length, type of pile, length of foundation pile and other information related to cost calculation (if any), should be included in the detailed or breakdown bill of quantities.

Besides, for works already included in the investment portfolio promulgated by competent authorities, the units of measurement used for quantity takeoff must comply with the corresponding units used in the investment book of record already in circulation. When taking off the quantity in ratio to the designed output, technical specifications or service capacity of a construction work, descriptive information should clarify the properties, characteristics and types of materials used as specified in the basic design and other necessary requirements.

View more details at Circular No. 17/2019/TT-BXD of the Ministry of Construction of Vietnam, effective from February 15, 2020.

Thu Ba

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

52 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;