The construction budget for the local housing development program is determined according to the following formula:
CT = C1 + C2
CT: is the total cost for establishing, verifying, managing, and announcing the housing development program.
C1: is the total cost to establish the housing development program, determined as follows:
C1 = Cchuan x H1 x H2 x K
Where:
- Cchuan = 400 (million VND): is the cost to establish the housing development program for a standard area.- H1: is the coefficient for work conditions and the level of economic - social development of the locality.- H2: is the coefficient for the scale of the natural area of the locality.- K: is the adjustment coefficient for the consumer price level.
C2: is the total cost for verifying, managing, and announcing the program, calculated as 15.6% of C1.
Details can be found at Circular 19/2016/TT-BXD, effective from August 15, 2016.