Hanoi-Vietnam: The time limit for submitting documents on settlement of a completed project under Circular 32

On October 24, 2016, the Vietnam Ministry of Agriculture and Rural Development issued Circular 32/2016/TT-BNNPTNT stipulating the settlement of completed projects funded by state capital under the management of the Ministry of Agriculture and Rural Development.

The time limit for submitting documents on settlement of a completed project in Vietnam is calculated from the date of signing the handover minutes for use; the time for verification and approval is calculated from the date the verification agency receives full documents from the investor. The maximum time limit is specified as follows:

Unit: months

Project Type Maximum time limit for submitting documents on settlement of projects for approval (including audit time) Maximum time limit for verification and approval
Projects of national significance 09 07
Group A projects 09 04
Group B projects 06 02
Group C projects 03 01

The power to approve the settlement may be found in Circular 32/2016/TT-BNNPTNT effective from December 15, 2016.

- Thanh Lam -

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;