Decree 99: 08 Contents of inspection of the implementation of planning in Vietnam

This is a notable content in Circular 08/2020/TT-BTNMT on the inspection of the implementation of policies, strategies, planning, and plans in Vietnam.

Quy định 08 nội dung kiểm tra việc thực hiện quy hoạch , Nghị định 99/2006/NĐ-CP

Decree 99: 08 Contents of inspection of the implementation of planning in Vietnam (Illustrative image)

Decree 99/2006/ND-CP prescribes the contents of inspection of the implementation of planning in Vietnam:

- Planning implementation schedule;

- Results and progress in implementing key investment programs and projects;

- Results and progress in achieving the main objectives and products of the planning;

- Results and progress in implementing solutions and mechanisms to achieve planning goals;

- Violations and weaknesses in planning implementation;

- Planning implementation results; limitations and reasons for non-implementation or poor implementation of the planning;

- Responsibilities of agencies, organizations, and authorized individuals in organizing the implementation of the planning (including the responsibilities of the lead agency and the responsibilities of related agencies);

- The suitability of the planning with the strategy used as a basis for planning and with socio-economic conditions.

Additionally, this Decree also regulates the inspection contents for plan implementation in Vietnam  as follows:

- Plan implementation schedule;

- Results and progress in achieving the plan's objectives;

- Results and progress in meeting mandatory targets and organizational measures for plan implementation;

- Results and progress in implementing key projects of the plan;

- Violations and weaknesses in plan implementation;

- Plan implementation results; limitations and reasons for non-implementation or poor implementation of the plan;

- Responsibilities of agencies, organizations, and authorized individuals in performing the tasks of plan implementation (including the responsibilities of the lead agency and the responsibilities of related agencies);

- The suitability of the plan with the planning used as a basis for the plan and with socio-economic conditions.

Details can be found in Decree 99/2006/ND-CP which comes into force in Vietnam from October 15, 2006.

Ty Na

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;