This is the content stipulated in Circular 11/2017/TT-BXD issued by the Ministry of Construction on October 16, 2017, providing regulations on the technical safety inspection procedures for slip form systems.
Accordingly, Circular 11 stipulates that the following conditions must be ensured when conducting inspections:
- The slip form system must be installed on-site and ready for inspection.- The hydraulic jacks used in the system must have been individually inspected for lifting capacity and component mechanism (as per Appendix C).- The technical documentation of the slip form system must be complete as per regulations.- Environmental sanitation and weather conditions must be sufficient to ensure that they do not affect the test results.- Occupational safety and hygiene conditions must meet the requirements to operate the slip form system for inspection purposes.
See details in Circular 11/2017/TT-BXD, effective from December 1, 2017.
-Thao Uyen-
Address: | 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City |
Phone: | (028) 7302 2286 |
E-mail: | info@lawnet.vn |