Recently, the Government of Vietnam has issued Decree No. 137/2013/NĐ-CP detailing implementation of a number of Articles of the Electricity Law, and the Law amending and supplementing a number of articles of the Electricity Law.

cấp GP tư vấn đầu tư xây dựng công trình nhà máy thủy điện, Nghị định 137/2013/NĐ-CP

Specifically, according to Article 39 of Decree No. 137/2013/NĐ-CP of Vietnam’s Government, organizations registering for advisory of investment in construction of Hydro-power plans, apart from general conditions specified in Article 28 of this Decree, must satisfy the following conditions:

1. Being an advisory organization in a specialized branch, having professional capacity of technology and hydro-power plant works, analysis of technique, economy and finance of projects, environmental impact assessments.

2. Having a contingent of advisory experts including major advisory experts and other advisory experts having experiences in equipment of hydraulic works, electric equipment, water treatment, automatic control, hydraulic works, and hydrology, hydraulic energy, Hydrometeorological, geologist of works, geological technique, structure and organization of construction of hydro-power plants and fields related to types of hydro-power plants.

3. Major advisory experts must have university diplomas or higher in electricity, hydro-power, irrigation, geological, environmental, economic, financial or similar branches and worked in the field of advisory for at least 5 years, and participated in designing at least one project of hydro-power plant with equivalent capacity and possess suitable construction-practice certificate.

4. Major advisory expert, who does task of the main responsible advisory expert, apart from conditions specified at Clause 3 of this Article, must have been head of a scheme, or main responsible for designing project on Hydro-power plant with equivalent capacity or participated in designing at least three projects on Hydro-power plants with equivalent capacity.

5. Having necessary equipment, technical means, and application software for advisory of investment in construction of Hydro-power plant works.

6. Having number of main advisory experts under ranks of Hydro-power works as follow:

- Rank 1: Having 25 experts or more, including at least 01 main responsible advisory expert;

- Rank 2: Having 20 experts or more, including at least 01 main responsible advisory expert;

- Rank 3: Having 15 experts or more, including at least 01 main responsible advisory expert;

- Rank 4: Having 10 experts or more, including at least 01 main responsible advisory expert.

View details at Decree No. 137/2013/NĐ-CP of Vietnam’s Government, effective from December 10, 2013.

Ty Na

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

36 lượt xem



Related Document
  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;