Circular 34: Regime of reporting by Vietnam Electricity Group

The regime of reporting by Vietnam Electricity Group is stipulated in Circular 34/2011/TT-BCT stipulating the formulation and implementation of the electricity supply plan when the national power system lacks electricity sources, issued by the Ministry of Industry and Trade on September 07, 2011.

policies  report  of  Vietnam  Electricity  Group,  Circular  34/2011/TT-BCT

Circular 34: Regime of reporting by Vietnam Electricity Group (illustrative image)

Article 20 of Circular 34/2011/TT-BCT regulates the regime of reporting by Vietnam Electricity Group as follows:

1. Weekly report

Before 16:00 on Friday of week W, the Vietnam Electricity Group is responsible for reporting to the Electricity Regulatory Authority of Vietnam on the status of electricity supply and load reduction in the national power system from Friday of week W-1 to Thursday of week W, including the following contents:

- Electricity output, available capacity of the system and the electricity output, capacity distribution for the electricity corporations within the week;

- Peak capacity, daily electricity output, and total electricity output of the entire system and each electricity corporation within the week.

The weekly report of the Vietnam Electricity Group shall be made in the weekly report template about the status of electricity supply and load reduction as prescribed in Appendix 3 issued together with Circular 34/2011/TT-BCT.

2. Monthly report

Before the 10th of every month, the Vietnam Electricity Group is responsible for reporting to the Ministry of Industry and Trade and the Electricity Regulatory Authority of Vietnam on the status of the electricity supply of the previous month, including the following contents:

- Electricity output, available capacity of the system, and the electricity output, capacity distribution for the electricity corporations each week within the month;

- Peak capacity, weekly electricity output, and total electricity output of the system and by each electricity corporation within the month;

- Estimated electricity output, peak capacity reduced by each electricity corporation and of the whole system each week within the month;

- Summary and estimation of total reduced electricity output, peak capacity for electrical loads of the entire system within the month;

- Analyses and clarification of the reasons in case the actual electricity output of the entire system differs from the approved monthly and annual operation plan by 5% or more.

The monthly report of the Vietnam Electricity Group shall be made in the monthly report template about the status of electricity supply and load reduction as prescribed in Appendix 3 issued together with Circular 34/2011/TT-BCT.

More details can be found in Circular 34/2011/TT-BCT effective from October 24, 2011.

Thuy Tram

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;