Order on the construction of urgent works: What does it contain?

According to current regulations, please inform me of the contents of an emergency construction order.

According to Clause 2, Article 58 of Decree 15/2021/ND-CP, the emergency construction order shall be documented in writing, including the following contents:

- Purpose of construction;

- Construction site;

- Person assigned to manage and execute the construction project;

- Construction timeline and estimated costs;

- Resources available for execution and other relevant necessary requirements.

Sincerely!

Related Posts
LawNet
What are conditions for issuing bidding documents used for investor selection in Vietnam?
LawNet
Is salt production one of the business lines given investment incentives in Vietnam?
LawNet
Vietnam: What are the regulations on the cost estimate for the construction bid?
LawNet
Suspension of investment projects in Vietnam
LawNet
What are entities from which investors participating in bidding in Vietnam must display legal and financial independence?
LawNet
What are the procedures for preparation of the proposal documentation for execution of a PPP project in Vietnam?
LawNet
What are regulations on contents of the construction estimate in Vietnam?
LawNet
Principles of allocation of investment capital included in the midterm and annual public for programs and projects in Vietnam
LawNet
Procedures for online contractor selection under single-stage and two-envelope bidding procedure in Vietnam
LawNet
What is the format of table for monitoring progress of investor selection activities in Vietnam under Decree 115?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;