Regulations on conditions for putting works and work items into operation and use

Decree 06/2021/ND-CP guidance on quality management, construction and maintenance of construction works with regulations on conditions for putting works and work items into operation and use.

Conditional acceptance and partial acceptance of construction works

Pursuant to the provisions of Clause 2, Article 23 of Decree 06/2021/ND-CP guiding the quality management, construction and maintenance of construction works, the regulations on conditional acceptance, acceptance of each Construction works:

Conditional acceptance and partial acceptance of construction works:

- Investors are entitled to decide to carry out the acceptance of work items and construction works when the capital construction has been completed according to the design requirements but there are still some quality problems which do not affect the bearing capacity, useful life and performance of the works and ensure that the works are eligible for safe operation and comply with relevant regulations of law. The acceptance result must be certified in writing as prescribed in Clause 6 of this Article and specifies the issues related to the quality that need rectifying or the building tasks that need continuing to be performed and the time for such tasks are fulfilled, the requirements for the limit of the operation of the construction (if any).] The investor shall conduct acceptance testing of the completion of works when there are shortcomings in terms of quality that have been remedied or the rest of building tasks that have been completed;

- When part of the construction work is completed and satisfies the conditions prescribed in Clause 1 of this Article, the investor may decide to accept such part in order to put it into temporary operation. The results of the pre-acceptance test must be certified in writing according to the contents prescribed in Clause 6 of this Article, clearly stating the parts of the to be-tested works. The investor shall continue the construction and acceptance of the remaining work items according to the design.

Work item in Vietnam

Conditions for bringing the works, work items into operation

In Clause 3, Article 23 of Decree No. 06/2021/ND-CP guiding the quality management, construction and maintenance of construction works stipulates the conditions for putting works and work items into operation. , specifically used as follows:

Conditions for bringing the work/work item into operation:

- The works, work items accepted as prescribed in clause 1, clause 2 of this Article;

- For works specified in Clause 1, Article 24 of this Decree, competent state agencies specified in Clause 2. For the works using public investment capital or state capital other than public investment, the investor is only permitted to finalize the construction contract after issuing the written approval of acceptance result mentioned above. For the works under the PPP project, the written approval for the acceptance result is the basis for the PPP project enterprise to prepare dossier to request the confirmation of work completion.

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

161 lượt xem
  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286