On February 1, 2025, the Minister of Industry and Trade of Vietnam issued Circular 16/2025/TT-BCT stipulating the operation of the competitive electricity market.
According to the regulations specified in Circular 16/2025/TT-BCT, the termination of participation in the competitive electricity market is as follows:
- Circumstances for termination of participation in the electricity market
+ A power plant may terminate participation in the electricity market under the following circumstances:
++ As proposed by the electricity generating unit owning the power plant in the event that the power plant completely ceases operation or the power plant cannot maintain and is unable to restore the installed capacity as per the registered information for participation in the electricity market within a duration of 1 year;
++ The power operation license in the field of electricity generation for the power plant is revoked or expires.
+ The wholesale electricity purchasing unit ceases to purchase electricity at delivery points within the scope of the electricity market, or the power operation license in the fields of wholesale and retail electricity is revoked or expires.
- In cases where the power operation license is revoked, the cessation time for participation in the electricity market of the electricity generating unit or the wholesale electricity purchasing unit is calculated from the time the power operation license is revoked per the decision of the competent authority. In other cases, at least 30 days before the intended cessation of participation in the electricity market, the market participant must send a written proposal to terminate participation in the electricity market to the Electricity and Market System Operator.
- Within 10 days from receiving the written notification proposing termination of participation in the electricity market from the market participant, the Electricity and Market System Operator is responsible for reviewing, deciding, and reporting to the State Electricity Regulatory Agency for supervision of the execution.
- The Electricity and Market System Operator is responsible for archiving records and publishing information on the electricity market's electronic portal regarding the termination of participation by the market member.
More details can be found in Circular 16/2025/TT-BCT, effective from February 1, 2025.