On September 21, 2017, the Ministry of Finance issued Circular 94/2017/TT-BTC specifying the procedures for the release of reserved power generators.
Process for releasing reserve generators as prescribed by Circular 94 is implemented as follows:
- Before releasing the generator: Prepare necessary tools, equipment, and documents, books, and records related to the release of the generator.
- Reserve generators released from the national stockpile must ensure quality according to regulations, have full relevant documents, books, and records, and adhere to the following principles:
- First in first out, last in last out; ensure the correct quantity and type. In other cases, there must be written direction from the directly managing superior agency;- Within the same batch at a storage location, release the generators that were tested and checked when received first, then release other generators.
See details in Circular 94/2017/TT-BTC effective from November 10, 2017.