This is a notable content stipulated in Circular 17/2013/TT-BVHTTDL guiding the determination of costs for the preparation of planning, projects, and economic-technical reports for the preservation, restoration, and rehabilitation of relics.
The costs for project preparation, economic-technical reports for the preservation and renovation of relics are specified in Circular 17/2013/TT-BVHTTDL as follows:
Source: Internet
- Costs for project preparation, economic-technical reports for the preservation and renovation of national relics, provincial relics are calculated based on the cost norms for project preparation, economic-technical investment reports for civil works issued by the Ministry of Construction effective at the time of application;- Costs for project preparation, economic-technical reports for the preservation and renovation of special national relics are calculated based on the cost norms for project preparation, economic-technical investment reports for civil works issued by the Ministry of Construction effective at the time of application and multiplied by coefficient K = 1.3.
In addition, Circular 17 also stipulates the costs for project preparation, economic-technical reports for the restoration of relics as follows:
- Costs for project preparation, economic-technical reports for the restoration of special national relics, national relics, provincial relics are calculated based on the cost norms specified in Clause 1, Article 7, multiplied by coefficient K = 1.2.- Costs for project preparation, economic-technical reports for the preservation, renovation, restoration of relics before tax are calculated by the total costs for preservation, renovation, restoration of the works and interior-worship items of the relics before value-added tax, multiplied by the percentage (%) corresponding to the cost norms for project preparation, economic-technical reports for preservation, renovation, restoration of relics.
Note: In case a project, economic-technical report has different contents (preservation, renovation, restoration), the determination of the coefficient for the project, economic-technical report is determined by separating the volume of each part according to a preliminary investment report prepared first and adjusted after the project, economic-technical report is approved.
See more specific regulations in Circular 17/2013/TT-BVHTTDL effective from February 18, 2014.